SELECTED PROJECT

DLA Phillips Fox Solicitors Office

Date:
2008
Duration:
24 weeks
Location:
L 28 and 29 at Waterfront Place, Brisbane
Design:
Geyer
Size:
2000m2
Value:
$1.7M
Industry:
CORPORATE
Team:

Operation Manager: Ben Scott
Project Manager: Jim Bryden
Site Foreman: Tim Filmer

This particular office refurbishment was the client’s third project with us in three years. Due to expanding numbers, this prestigious firm required another restructure to cater for their staff. We were already familiar with the client and worked towards achieving their end goal within the set time frame. The new space provided ample room for employees and clients without losing the understated elegance that reflects the company’s image.

“Quadric performed admirably on a very difficult project, requiring close communication with the client and the project team to ensure the construction programme was maintained and the client was not unduly inconvenienced. Quadric completed the project on time and with minimal variations or design changes that in any case were changes made at the client’s request. We cannot fault Quadric’s quality of workmanship, level of site supervision, contract administration and general attitude and professionalism. We have no hesitation in recommending them for future projects.”

Tony Alberti Regional Manager QLD Geyer Pty Ltd