The Griffith University M07 Building was originally broken into two sections: a tired and aged office space and an external storage area. This project enclosed the storage area to extend the internal space and create a new Laptop Lounge and modern office space for students and staff. It incorporates functionality for learning with sleek aesthetics to encourage use from a range of demographics. Incorporating a new concrete staircase and suspended steel walkway, this project clearly demonstrates what can be achieved by having the project delivered by a fitout contractor who has the skills and expertise to conduct true building works.
SELECTED PROJECT
Griffith University M07 Building
Date:
2009
Duration:
24 Weeks
Location:
Mt Gravatt Campus
Design:
Suters Architects
Size:
2100m2
Value:
$2.2M
Industry:
EDUCATION
Team:
Construction Manager: Jim Bryden
Project Manager: Peter Kowald
Site Foreman: Grant Hartland